In terms of schedule, more work has been done than planned.
<u>Explanation:</u>
Given information,
Planned Value = 1000
Earned value = 1200
Actual Cost = 800
Budget at completion = 2000
Estimate at completion = 1333
The following is the explained calculation of estimate at calculation,
Planned Value, also called as Budgeted Cost of Work Scheduled is the unit of task that is supposed to be done within the specified amount of time.
Budgeted Cost of Work Performed is the earned value and it is the total unit of work that is actually been completed.
Actual cost is stated as the to-date cost of the completed task or work.
Budget at completion is the total budget of the project.
Estimate at completion helps to assess whether the project has been done as per the plan.
Therefore, 1600 is the expected final budget. So, on comparing the given values on the project we can conclude that more work has been done than planned.