As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly

operation to achieve an output of 240 units per eight-hour day.
Task times and precedence relationships are as follows:

Task Duration (minutes) Immediate Predecessor
a 0.2 -
b 0.4 a
c 0.2 b
d 0.4 -
e 1.2 d
f 1.2 c
g 1.0 e, f

Do each of the following:
(a) Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.)
(b) Determine the minimum number of stations needed. (Round your answer to the next whole number.)
(c) Assign tasks to workstations on the basis of the greatest number of following tasks. Use the longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
(d) Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 2 decimal places. Omit the "%" sign in your response.)

Business
1 answer:
ioda3 years ago
4 0

Answer:

A)Minimum = 0.2 minutes

Maximum = 4.6 minutes

Cycle time = = 2 minutes per unit

B) Number of Stations = 3

D) the percentage of idle time for the assignment in decimal = 0.43

Explanation:

A) Operating output = 240 units per 8hours.

Converting to per hour, we get; 240/8 = 30 units per hour.

Minimum cycle time = longest task time

Maximum cycle time = sum of task times

Minimum = 0.2 minutes

Maximum = 0.2 + 0.4 + 0.2 + 0.4 + 1.2 + 1.2 + 1.0 = 4.6 minutes

Now, operational time(OT) is 8 hours a day. Converting that to minutes, we have =60x8 = 480 minutes

Cycle time(CT) = OT (per day) /desired output

Therefore, calculated cycle time = 480/240

= 2 minutes per unit

B) Number of stations = Maximum time / CT

= 4.6/2 = 2.3 which is approximately 3 stations

C) The task diagram is drawn in image 1 attached. Therefore, we can assign tasks based in the greatest number of following tasks as follows;

Task Number of following tasks

a 4

b 3

c 2

d 2

e 1

f 1

g 0

D) for the idle time from the assigned tasks in "c" above, from the "image 2" attached; the percentage of the idle time will be=

Total remaining time of tasks without remaining feasibility tasks/ {(number of these tasks) x(CT)}

Which gives percentage of idle time = (0.8 + 0.8 + 0.8 + 1.0)/{(4)x(2)}

= 3.4/8 = 42.5%

Since we are to convert to decimal,

= 0.425 approximately 0.43

You might be interested in
Which of the following is not an objective of proactive scanning? Identify and define potential opportunities and threats. Paint
tigry1 [53]

The option that is not an objective of proactive scanning is: Paint a picture of the future 20+ years into the future.

<h3>What is proactive scanning?</h3>

Proactive scanning is the use of automated tools to detect suspicious programs/contents in library, driver, and executable files.

This scanning method can be used to detect threats and important events. They could also serve useful functions to employers and managers.

Learn more about proactive scanning here:

brainly.com/question/26199042

6 0
2 years ago
Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on
AlladinOne [14]

Answer:

Saddle Inc.

1. Overhead rate using the traditional (plantwide) approach is:

= $1.84

2. The overhead rates using activity-based costing approach are:

Machining = $72.49

Machine setup = $211.69

3. The difference in allocation between the two approaches:

Differences:

ABC approach        $121,808   $178,188   $299,996

Using plantwide     $110,400  $189,520  $299,920

Differences              $11,408    -$11,332             $76

Explanation:

a) Data and Calculations:

Total estimated overhead costs = $300,000

Machining activity = $195,000

Machine setup activity = $105,000

                             Standard   Custom     Total

Direct labor costs $60,000 $103,000  $163,000

Machine hours           1,400        1,290       2,690

Setup hours                    96          400          496

Overhead rate based on direct labor costs = $1.84 ($300,000/163,000)

Overhead rates using activity-based costing approach:

Machining = $72.49 ($195,000/2,690)

Machine setup = $211.69 ($105,000/496)

Allocation of overhead costs:

                                 Standard   Custom         Total

Using plantwide       $110,400  $189,520  $299,920

Using ABC:

Machining                $101,486    $93,512    $194,998

Machine setup           20,322      84,676      104,998

Total costs               $121,808   $178,188   $299,996

Differences:

ABC approach        $121,808   $178,188   $299,996

Using plantwide     $110,400  $189,520  $299,920

Differences               $11,408    -$11,332            $76

6 0
3 years ago
The test manual reports a reliability coefficient (r) of .92, which means:
Lady bird [3.3K]

In statistics, reliability refers to how consistent a measurement scale is overall. Measurement scales with high reliability scores would be able to produce similar results when tested with groups of samples similar to the initial testing conditions.  

Reliability scores are measured through reliability coefficient which spans from 0.0 to 1.0. What a reliability coefficient of 0.92 means is (B) 92% of the variance in scores is explained by real differences.

7 0
3 years ago
If the family decides to reduce its clothing budget by $200 a month, how much will the new clothing budget be? Round to the near
STALIN [3.7K]

Answer:

$970

Explanation:

6 0
3 years ago
The Larson and Gobeli study that compared projects that had been managed in a variety of structural types revealed that new prod
11Alexandr11 [23.1K]

Answer:

The correct answer is letter "C": Project organization.

Explanation:

Gobeli, D. and Larson, E. published in the <em>Project Management Journal</em> (1987) the <em>Relative effectiveness of different project structures</em> after their study on how projects are organized and how that organization affects the results of the team. According to them, superlative effectiveness is accomplished in project organization structures.

6 0
3 years ago
Other questions:
  • After reading the new account insert in his monthly​ statement, Tony Mercadante determined that the FDIC considers a joint accou
    6·1 answer
  • Which is an advantage of the sole proprietorship and partnership business models?
    5·1 answer
  • Indicate whether each scenario will affect the GDP deflator or the CPI for the United States. Check all that apply. Scenario Sho
    10·1 answer
  • Calculating Residual Income Pelican Manufacturing earned operating income last year as shown in the following income statement:
    10·1 answer
  • debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with information concerning p
    9·1 answer
  • West Corp. issued 20-year bonds two years ago at a coupon rate of 8.6 percent. The bonds make semiannual payments. If these bond
    5·1 answer
  • Suppose Bev's Bags makes two kinds of handbags—large and small. Bev rents an industrial space where she keeps the fabric, the in
    12·1 answer
  • For​ 2018, Winters Manufacturing uses machineminushours as the only overhead costminusallocation base. The direct cost rate is $
    11·1 answer
  • What are hard skills?
    5·1 answer
  • Q1: In about 200 words, write an essay analyzing the below case study using the SWOT framework.
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!