Answer: Elasticity of luxury weekend hotel packages in las vegas is -1.432.
Explanation:
Price elasticity of demand measures the responsiveness of quantity demanded to a change in the price of the good.
Mid point method-





Elasticity of luxury weekend hotel packages in las vegas is -1.432.
Answer:
a) 3X + 2Y = 36
b) X = 6 , Y = 9
c) 27
Explanation:
Individual consumes : X and Y
Spends : $36 per time period
unit cost : $3 per unit for X
$2 per unit for Y
utility function : U( X, Y ) = .5XY
<u>A) Budget equation mathematically</u>
X* Px + Y* Py = M
3X + 2Y = 36
Px and Py = unit cost for X and Y
M = Total spent ( revenue )
<u>b) Values of X and Y that will maximize utility </u>
Maximum utility ( MRS ) = Px / Py ,
MRS = MUx / MUy
= Y/X = 3/2
∴ 2Y = 3X
From BC : 6X = 36 ( X = 6 plug into mathematically equation above )
∴ X = 6 , hence Y = 9
<u>c) Total utility generated per unit of time </u>
U( X,Y ) = .5XY
= 0.5 * 6 * 9 = 27
Answer:
6.00 days
Explanation:
data provided
Inspection time = 3.7 days
Process time = 0.2 days
Move time = 1.3 days
Queue time = 0.8 days
The calculation of throughput time is given below:-
Throughput time = Inspection time + Process time + Move time + Queue time
= 3.7 days + 0.2 days + 1.3 days + 0.8 days
= 6.00 days
Here, we added the inspection time, process time , move time and queue time to reach at throughput time and we ignore the time spent waiting to be worked on in the factory as it is not relevant.
Answer:
Estimated manufacturing overhead rate= $32 per labor hour
Explanation:
Giving the following information:
The estimated factory overhead costs $ 2,496,000. Estimated labor hours 78,000.
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 2496000/78000= $32 per labor hour