I believe the answer is:
- What can go wrong?
This question is asked to find out the potential risk that may occur after purchasing the product.
- What is the likely return?
This question is asked to find out potential benefit from consuming the product
-Is the risk worth the return?
<span>The purchase should be made only if the potential benefit would outweigh potential risk
</span>
Answer:
10%; 16%
Explanation:
Given that,
Real GDP in the first quarter of 2016 = $10 billion
Real GDP in the first quarter of 2017 = $11 billion
Increased from the fourth quarter of 2016 to the first quarter of 2017 = 4%
Growth rate from the first quarter of 2016 to first quarter of 2017:
= 
= 
= 10%
Real GDP growth rate is as follows:
= 4% × 4
= 16%
Explanation:
POSDCORB is an acronym which means Planning, Organizing, Staffing, Directing, Coordinating, Reporting and Budgeting
Answer:
If discount rate is 11.7% Project B should be accepted.
If discount rate is 13.5% both projects should be rejected
Explanation:
If the Net present value of Project A is higher than that of project B, we will accept project A and vice versa.
<u>Under 11.7% Discount Rate</u>
Net Present Value-Project A = -82000 + 34000 / 1.117 + 34000 / 1.117² + 34000 / 1.117³ = $85.099
Net Present Value-Project B = -82000 + 115000 / 1.117³ = $516.029
Project B should be accepted as it has a higher NPV.
<u />
<u>Under 13.5% Discount Rate</u>
Net present Value-Project A = -82000 + 34000 / 1.135 + 34000 / 1.135² + 34000 / 1.135³ = - $2397.49
Net Present Value-Project B = -82000 + 115000 / 1.135³ = - $3347.91
Both projects should be rejected as both have negative NPVs