Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days
Answer:
mean= 73.167
mode= 85
range= 47
median= 78.5
Step-by-step explanation:
46 58 72 85 85 93
mean= 73.167
mode= 85
range= 47
median= 78.5
Answer:
The answer is 238 :)
Step-by-step explanation:
I think the pdf image can give you the answers you are looking for.
Answer:
y = 1x+14
Step-by-step explanation:
The slope intercept form is
y = mx+b where m is the slope and b is the y intercept
y = 1x+b
Substitute the point into the equation
10 = -4+b
Add 4 to each side
10+4 = -4+b+4
14 = b
y = x+14