Step b is wrong. The slope is the change in y over the change in x.
Step b should be (18- 8)/( 10-6)
= 10/4
= 5/2
Answer:
the probability of no defects in 10 feet of steel = 0.1353
Step-by-step explanation:
GIven that:
A roll of steel is manufactured on a processing line. The anticipated number of defects in a 10-foot segment of this roll is two.
Let consider β to be the average value for defecting
So;
β = 2
Assuming Y to be the random variable which signifies the anticipated number of defects in a 10-foot segment of this roll.
Thus, y follows a poisson distribution as number of defect is infinite with the average value of β = 2
i.e

the probability mass function can be represented as follows:

where;
y = 0,1,2,3 ...
Hence, the probability of no defects in 10 feet of steel
y = 0


P(y =0) = 0.1353
Gfryudsgjxeujhhhdsethjhyui
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.
9514 1404 393
Answer:
- absolute error: 0.4 kg
- relative error: 6.1%
Step-by-step explanation:
The absolute error is the difference between the estimate and the actual weight:
7.0 kg -6.6 kg = 0.4 kg . . . . absolute error
__
The relative error is the ratio of the absolute error to the actual weight:
(0.4 kg)/(6.6 kg) × 100% = 6.060606...% ≈ 6.1% . . . . relative error