Answer:
Step-by-step explanation:
ACB is an inscribed angle
so ∠ACB = 1/2 mAB
Hence we got

Give us a picture of XYZ and some choices for the answer,
and you'll have yourself a question that we can work with.
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer is A.
the two angles are share a side (side BC)
hope it helps
Answer:
y=2x
Step-by-step explanation:
Direct variation is such that y=kx where k is the rate of change. In direct variation the graph must cross the origin (0,0) meaning that the y-intercept is zero. The only equation that satisfies the definition of direct variation is y=2x.