Answer:
The correct answer is A.
Explanation:
Giving the following information:
Mcmurtry Corporation sells a product for $110 per unit. The product's current sales are 12,200 units and its break-even sales are 10,614 units.
<u>The margin of safety is the number of units or amount of dollars that provide genuine profit to the company. It is the "margin" that gives room to try new strategies</u>.
It is calculated using the following formula:
Margin of safety ratio= (current sales level - break-even point)/current sales level
Margin of safety ratio= (12,200 - 10,614) / 12,200
Margin of safety ratio= 0.13=13%
Answer:
The standard deviation of the returns on the stock is 15.56%(Approx).
Explanation:
Expected Return=Respective return*Respective probability
=(20.4*0.67)+(-12.7*0.33)=9.477%
probability Return probability*(Return-Expected Return)^2
0.67 20.4 0.67*(20.4-9.477)^2=79.93899243
0.33 -12.7 0.33*(-12.7-9.477)^2=162.3003786
Total=242.239371%
Standard deviation=[Total probability*(Return-Expected Return)^2/Total probability]^(1/2)
=15.56%(Approx).
Such considerations include understanding of:
the reasons for and objectives of sampling.
the relationship between accuracy and precision.
the reliability of estimates with varying sample size.
the determination of safe sample sizes for surveys.
the variability of data.
Answer: c. $20,000
Explanation:
The Loss on Realization is monies accrued after assets have been sold off at less than their original value and in Calculating it, the following formula is used,
Loss on realization = Total Capital Balances after payment of liabilities minus - balance
Slotting in the figures therefore we have,
Loss on realization = $40,000 + $70,000 - $80,000
= $30,000 was the total loss on Realization
Seeing as Antonio and Barbara are partners who share income in the ratio of 1:2 we allocate to Barbara as follows,
Barbara = $30,000 * 2/(1+2)
= $20,000
Therefore option C is correct.
Answer: The common constraints faced by project managers are project scope, cost and time.
Explanations:
The three main constraints faced by project managers are the project scope, cost and time. These constraints affect the quality of a project. In high quality projects, the product is delivered within its scope at the required budget and on time.
The constraints are usually connected to one another. For example, an increase in the project scope will require an increase in cost and time. Also, accelerating the project timeline may lead to a reduction in the project costs but also lower the scope.
A trade off in project occurs when one constraint is reduced so as to increase another constraint. For trade-offs to be successful, project managers should take time to scrutinize the organization's objectives and the expectations of the project by using a structure that allows the project manager look at other options for the constraints and find the greatest balance among the constraints and organizational goals.