Answer:
Big data analytics
Explanation:
Big data analytics is the process of analysing large data sets (big data) to get insights such as hidden patterns, correlations, and market trends. This information is used to make business decisions.
Big data analytics bus used to study structured data sets, unstructured data sets, and semi-structured data sets.
This form of data processing bis used accros different industries including banking, insurance, health-care, communication, education, and manufacturing.
Answer:
$2,600
Explanation:
Calculation of the value of the company's inventory at the lower of cost or market.
Current FIFO inventory ×Net realizable value
Where,
Current FIFO inventory= 200 units
Net realizable value $13 per unit
Therefore,
200 units *$13 per unit = $2,600.
Lower cost of market can be said to mean that the inventory cost at either the purchase cost or replacement value .
Bases on the information given in the question, replacement cost is lower or lesser than the purchase cost which is why the inventory units are been cost at the replacement value of $13 each.
If the company decided to have its production cut into half of its original value, this will most likely be causing the unemployment of those who originally stayed with the company because of the company will most likely decide to fire some of its people to cut costs. In this essence, the country to which the company manufactures the product will have an increase in the unemployment percentage.
Answer:
Myron gains, while the bank loses.
Explanation:
Fallen in prices is usually cause by deflation i.e a general decrease in the prices of goods and services which enhances the purchasing power of money.
In this case, 5% fall in price will increase the value of the Myron investment with bank and caused bank more money .
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.