Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
Step-by-step explanation:
X= 12
Answer:
They represent the rise and run of the graph.
Step-by-step explanation:
The difference between the x-axis of the points represents the "run" of the graph (or how much you should run along x-axis to get to the next point.)
The difference between the y-axis of of the points represents the "rise" of the graph (or how much you should rise up the y-xis to get to the next point).
The ratio of rise to run is the slope of the graph, which tells us how many steps should we take on the y-axis for every step we move forward on the x-axis.
Answer:
7
Step-by-step explanation:
Answer:

Step-by-step explanation:
Given


Required
Find the measure of a
Since there is no diagram to support the question, we'll assume that:

This gives:

Subtract 22 from both sides