Hexagon = 6 sides = 6 x 4 = 24
Octagon = 8 sides = 8
Dodecagons = 12 x 5 = 60
24 + 8 + 60 = 92 IN TOTAL
Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.
Answer: I Hope some one helps you out
Step-by-step explanation:Y
Answer: 31°
Since <DAB = 55° and <CAB = 24°, subtract 24 from 55.
55 - 24 = 31