Answer:
(B) $18.40
Explanation:
we build the equation system and solve for variable overhead
we must understand that overhead unit cost if calculate as follow:
variable overhead + fixed overhead / volume
so:

We rearrange:

We equalize:

And now we solve:
(33.8 - VMO) x 3 = 64.6 - VMO
101.4 - 3 VMO = 64.6 - VMO
36.8 = 2VMO = 18.4
Answer: c.
Explanation: The unemployment rate may underestimate the true extent of unemployment if there are a large number of people working in the underground economy . While the underground economy also known as the black economy may conjure up images of drug deals and prostitution rings, the term actually has much broader scope. It refers not only to illegal economic activity, but all economic activity that goes unreported to government authorities and consequently, avoids being taxed. one of the primary reasons the underground economy exists is that people are trying to evade taxes. But increased government regulations that can make the cost of doing business higher also create an incentive to avoid reporting certain economic activity to the government. An increase in the number of unemployed increases the number of people who work in the black economy because they have more time. On the other hand, an increase in unemployment implies a decrease in the shadow economy.
Marketers use this kind of data validation:
A. time series sales model
Explanation:
The time series sales model usually works for marketing campaigns because ultimately the marketeer wants to understand how many sales are being converted from primary and secondary sources.
This then leads to the cost and result assessment of the firm.
So, the time series sales model tells when how many sales are being done with some semblance of a filter for the secondary sources from the data of the marketer that they would have.
Answer
The answer and procedures of the exercise are attached in the following archives.
Step-by-step explanation:
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.
Answer:
45
Explanation:
The formula to compute the number of parts is shown below:
= Demand × lead time × (1 + safety factor) ÷ kanban cards
= 300 units × 45 minutes × (1 + 20%) ÷ 6
= 300 × 0.75 hours × 1.2 ÷ 6
= 45
The 45 minutes would be 0.75 hours i.e 45 minutes ÷ 60 minutes = 0.75 hours.
So we consider all the components which are given in the question. Hence, all the information is relevant