Couldn't show it all but help​

Mathematics
1 answer:
noname [10]3 years ago
5 0

Answer:

I don’t know I can see it all

Step-by-step explanation:

Sry tho try to take another pic

You might be interested in
Find g (x), where g(x) is the reflection across the x-axis of f(x) = 7 [x+2]-6
Anvisha [2.4K]
Answer:
I’m pretty sure it’s g(x) = 7|x-2| -6
Hope this helps!
8 0
2 years ago
PLEASE HELP 17 POINTS FOR ANYONE WHO CAN SOLVE ALL THESE
faust18 [17]
1) $19.18
2) $948.75
3)$39.49
3 0
3 years ago
Read 2 more answers
4(4 divided by 2 + 14)
kap26 [50]

Answer:

64

Step-by-step explanation:

6 0
2 years ago
Read 2 more answers
4. Find the values of x and y<br>following:complex number. <br><br>(X,Y) = (3,2)-(1,4)<br>​
Sergeeva-Olga [200]

Answer:

x=2 and y= -2

Step-by-step explanation:

(x,y)=(3-1,2-4)

(x,y)=(2,-2)

x=2

y= -2

7 0
3 years ago
HELP MEH PLS ps the answer is not 2.5
mash [69]
<h3>Answer: Approximately 2.483 hours </h3>

=========================================================

Explanation:

Justin can do the full project by himself in 6 hours. This means his rate is 1/6 of a project per hour. In other words, in one hour, he gets 1/6 of the project done.

Jason can do the full project in 9 hours, so his rate is 1/9 of a project per hour, if he works alone.

Jacob's rate is 1/8 of a project per hour since he can get the job done in 8 hours if he works alone.

-----------

So we have these unit rates

  • Justin's rate = 1/6
  • Jason's rate = 1/9
  • Jacob's rate = 1/8

The units for each rate is projects per hour.

The total rate is

1/6 + 1/9 + 1/8

12/72 + 8/72 + 9/72

(12+8+9)/72

29/27

If the three brothers work together, and no person slows down another, then the rate at which they work together is 29/72 projects per hour. In short, they get 29/72 of the project done in 1 hour.

Let x be the number of hours needed to get the project done if they work together. Multiplying this time value with the rate leads to the amount of the project done. We want the result to be 1 to indicate a full project is complete.

(rate)*(time) = amount done

(rate)*(time) = 1 full project

(29/72)*(x) = 1

x = 1*(72/29)

x = 72/29

x = 2.48275862068966

x = 2.483

It'll take about 2.483 hours to get the job done if they work together. Again this assumes that they don't get in each others way to slow each other down.

8 0
3 years ago
Read 2 more answers
Other questions:
  • If you sum the numbers from 1 to 36, the sum is ?
    14·1 answer
  • 4 x 2x 4 being length and 2x being width
    9·1 answer
  • 2 Points
    8·1 answer
  • 60 people will be attending a dinner party. each table at the party can seat 8 people. how many tables are needed? write and sol
    13·2 answers
  • 7x +2y = 24<br> 8x+2y= 30<br> What is x and y
    12·2 answers
  • Is (3,2) a solution of -8x-2y&lt;6
    10·2 answers
  • Which is 216 written as a power of a number?
    12·1 answer
  • So i need a example with a bar model and equations
    13·1 answer
  • Find the geometric mean of the pair of numbers. Give your answer in simplest radical form.
    14·1 answer
  • Please help me with this question. I will also give brainliest!
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!