The minimal completion time for the activities is the shortest possible time for all the activities to be finished. In doing this, we look at the path that would require the greatest amount of time. At the START node, we choose the path that would take the longest which is 7 days leading to ACTIVITY D. Next, we choose the path leading to ACTIVITY B which takes 5 days. Then, we move to ACTIVITY C taking 5 days and finally, reach the END which would take 6 days. So, the minimal completion time is:
7 + 5 + 5 + 6 = 23 days
Find out the statement true regarding the diagram given in the question
Answer
the statement is true regarding the diagram is
m∠WXY + m∠YXZ = 180°
REASON
As shown in the diagram
∠WXY and ∠ YXZ are supplementary angles.
Supplementary angle definition
Two Angles are said to be Supplementary when there sum is equal to 180 °.
thus we get
m∠WXY + m ∠YXZ = 180 °
Therefore the m∠WXY + m∠YXZ = 180° is the true statement.