The effective annual rate is 8.33%.
we can calculate the effective nominal annual rate by using this formula;
r = e∧i - 1
e is the constant = 2.718
i = compounded annual nominal rate = 8% = 0.08
r = 2.718∧ (0.08) - 1
= 1.0833 - 1
= 0.0833 = 0.0833 x 100 = 8.33%
Answer: may be determined by subtracting the total variable cost from either the total cost at the low or high activity level
Explanation: In using the high-low method, the fixed cost may be determined by subtracting the total variable cost from either the total cost at the low or high activity level.
Answer:
A) economic order quantity ( order quantity model that will minimize the total holding cost and ordering costs ) =
=
= 122. 74 ≈ 122 ( optimal ordering quantity ) units
B) Annual holding cost = 23 * 122 / 2 = $1403
C ) Annual ordering costs = 1500/122 * 77 = $947
D ) The reorder point = daily demand * lead time = 50 * 3 = 150 units
Explanation:
Annual demand for connectors : 1500
ordering cost ( cost to place and process an order ) : $77
annual holding cost per unit : $23
A) economic order quantity ( order quantity model that will minimize the total holding cost and ordering costs ) =
=
= 122. 74 ≈ 122 ( optimal ordering quantity ) units
B) Annual holding cost = 23 * 122/2 = $1403
C ) Annual ordering costs = 1500 / 122 * 77 = $946.72 ≈ $947
D ) The reorder point = daily demand * lead time = 50 * 3 = 150 units
daily demand = 1500 / 300 = 50
lead time = 3
Answer:
Sell now, the company will be better off by $25,200
Explanation:
The effect of the action of shown below:-
Profits if sold now = Product Pound A × Sold pound
= 36,000 pounds × $8
= $288,000
If processed further Profits
= (36,000 x $14) - $241,200
= $262,800
Selling product A now = Profits if sold now - Further Profits
= $288,000 - $262,800
= $25,200
Answer:
Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.