a crane lifts a 450 kg concrete to the top of a 50 m building in 5 s. assuming g=10 m/s² calculate a) the potential energy of th
e concrete B):- the power developed by the crane
1 answer:
Answer:
Step-by-step explanation:
The work done changes the potential energy
ΔPE = mgΔh = 450(10)(50) = 225,000 = 225 kJ
power is the rate of doing work
P = 225000/5 = 45000 W = 45 kW