Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
Hi,
a=b+3
Step-by-step explanation:


Thus:
c+2b+8-4a=c-a-b-1
3b-3a=-9
<u>a=b+3</u>
So it’s -3 and the second one is +4
Hi! The temperature would be 18°.
There was a 4 hour period between 5 and 9 a.m.
So, I just took -10, and added 7 four times.
-10 + 7 + 7 + 7 + 7 = 18
Hope this helps you! Happy thanksgiving, here's a turkey!