Answer:
True 
Explanation:
For computing the cost of the completed jobs in a  job-order costing system we have to consider the actual direct materials cost,  actual direct labor cost, and the manufacturing overhead cost applied.
In mathematically,  
The total cost of completed job = Direct Material cost + Direct labor cost + manufacturing overhead cost
Therefore, the given statement is true
 
        
             
        
        
        
By asking questions and demonstration. In this way, you would be able to understand the instructions fully. With the help of demonstration, it will help you understand on what to do while by asking questions, it allows you to understand the whole procedure and its importance.
        
             
        
        
        
Answer:
Production for the third quarter   159,500
Explanation:
Sales for the period           161,000
Desired ending inventory    4,600
Total production needs     165,600
Beginning Inventory             (6,100)
Production for the third quarter   159,500
The sales for the period and the desired ending inventory are the total units we need for the quarted.
the beginning inventory reduces the production because are units we already have