Answer: 120 days
Step-by-step explanation:
A can complete it in 16 days.
=100/16 =6.25%/day.
B has ten days to do it.
10% every day is equal to 100/10.
So they would each contribute 16.25 percent per day as a group.
then for six days,
16.25*6 =97.50percent
97.50% of the work has been finished, in other words.
The amount of work left is now 100-97.5 = 2.5.
C finishes up the remaining job in 3 days
3.5% in 3 days, to be exact.
Consequently, he will finish his entire project in 120 days.
[2.5 * 40 = 100 percent; 40 * 3 = 120 days]
Answer:
Whatever is raised to the power of 0 is 1
SO the answer is 1
Answer:
B
Step-by-step explanation:
We are given the function:

And we want to determine the value of:

Let this value equal <em>a</em>. In other words:

Then by the definition of inverse functions:

Hence:

Solve for <em>a: </em>

By the Zero Product Property:

Hence:

Thus, f(9) = 225. Consequently, f⁻¹(225) = 9.
In conclusion, our answer is B.
Answer:
x=2 and y=1
Step-by-step explanation:
Rewrite equations:
y=−x+3;y=x−1
Step: Solve
y=−x+3
Step: Substitute−x+3foryiny=x−1:
y=x−1
−x+3=x−1
−x+3+−x=x−1+−x(Add -x to both sides)
−2x+3=−1
−2x+3+−3=−1+−3(Add -3 to both sides)
−2x=−4−2x−2=−4−2
(Divide both sides by -2)
x=2
Step: Substitute2forxiny=−x+3:
y=−x+3
y=−2+3
y=1(Simplify both sides of the equation)
Hope this Helps you :)
Answer:
Step-by-step explanation:
1) 4x + 3 <= 3x - 5
Subtract 3 from both sides
4x + 3-3 <= 3x - 5 -3
4x <= 3x - 8
Subtract 3x form both sides
4x - 3x <= 3x -3x - 8
x <= -8