<h3>Check out the diagram below for the proper labeling</h3>
The radius goes from the center to the edge of the circle.
The diameter is twice as long as the radius; it is a segment going through the center with both endpoints on the circle
The circumference is the distance around the circle. Think of it as the perimeter of the circle.
Answer:
"She lost her whey"
Step-by-step explanation:
I hate when it comes to explaining but I gave it my best!
(4^2)^4 is the same as (4^4)^2 because they’re both being squared and multiplied by the a number equaling to the same number, but written differently.
4^2=16 , whereas 4^4=256
HOWEVER
16^4=65536 and 246^2=65536.
Therefore both equal to the same number. It depends on the exponents, and multiplication. If it were to be a different exponent, then they wouldn’t have been the same
Answer: 250 miles
Step-by-step explanation: 440/8 = 50
50 x 5 = 250
Answer:
Expected project duration is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network.
Step-by-step explanation:
In project management, early start is the earliest moment at which a specific activity may start and early finish the earliest moment at which it can end. Early finish (es) is computed as:
EF = ES + d
where d is the activity duration and ES early start
Early start is computed as
ES: Max (EF-1)
or the maximum early start of predecessory activities.
Once we have calculated these values in the network for each activity , the early finish of last activity corresponds to the expected project duration, the earliest time in which we may finish the project if there are no issues.
Max project duration is open question as we could have infinite delays or never finish the project. Time variance in project duration may only be estimated once we have actual execution times of our project.
Slack time and critical path are obtained after obtaining the ES and EF but this info alone is not sufficient. We require either the late start or the late finish of the activities to calculate slack, Zaero slack activities, those that cannot be delayed form critical path and can only be obtained after having ES. EF. LS and LF