Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Answer:
correct option is a. $36,000
Explanation:
given data
labor cost = $360,000
move material per year = 600,000 pounds
to find out
material handling cost
solution
we find here first Labor Cost per pound of material that is express as
Labor Cost per pound of material = Labor Cost ÷ Number of Pounds of material .......................1
Labor Cost per pound of material = 
Labor Cost per pound of material = $ .6 per pound of material
=360000/600000= $0.6 per pound of material
so we can say that 60000 pounds are moved in March so cost will be
60000 pounds are move cost = 60000 × $0.6
60000 pounds are move cost = $36000
so correct option is a. $36,000
Answer:
Bonus.
Explanation:
Just as the name sounds, so is it an additional pay that is been given to an employee seen to appear above their regular earnings, this bonus is seen to be used by many organizations in different forms are categorically given to employees or a team that achieves significant goals. This little pay go a very long way in the life, performance and output of a team or employee. Also, employee morale, output and also motivation. Due to the positive returns from this act, a lot of organisations tends to practice this ritual consistently because every goal or target reached by an employee or or team brings the organisation closer to success.
<u>Solution and Explanation:</u>
a) No, it should not be included as the goods were shipped on 26th March and the terms were FOB shipping, it does not matter that customer receives it on 2 March
.
b) Yes, as the title of goods passes to houghton on 26th March as the terms were FOB shipping hence (450+30) $480 should be included.
c) Yes, $720 should be included in ending inventory as the goods will be shipped on 10th march
.
d) No, as the goods were on consignment
.
e) No, as the terms are FOB destination hence totle of goods passes to Houghton on March 2 hence shouls not be included.
f) Yes, as terms include FOB destination so titke passes to customer on March 2 hence is included at cost of $240.