The market-sharing pact or agreement negotiated by trading partners that give rise to voluntary quotas of exports aimed at protecting the importing country's domestic firms is called a <u>voluntary export restraint (VER)</u>.
<h3>What is voluntary export restraint (VER)?</h3>
Voluntary export restraints (VER) are export arrangements between exporting and importing countries so that the exporter agrees to limit the number of some exports.
VER allows the importing country's domestic firms to survive export dumping. It is the opposite of voluntary import expansions (VIE). VIE, which is a part of international trade agreements, allows for more imports by lowering tariffs or dropping quotas.
Thus, the market-sharing pact negotiated by trading partners allowing for voluntary quotas on exports is called <u>voluntary export restraint (VER)</u>.
Learn more about international trade agreements at brainly.com/question/1465144
The budget is $4,240.
There are 164 kittens and 24 puppies.
Let
x = amount spent on each kitten
y = amount spent on each puppy.
The cost for each puppy is twice a much as that for a kitten. Therefore
y = 2x (1)
The available amount is $4,240, therefore
164x + 24y = 4240 (2)
Substitute (1) into (2).
164x + 24(2x) = 4240
212x = 4240
x = $20
y = 2x = $40
Answer: $40 for each puppy.
In risk management, risk evaluation involve Risk resolution. The evaluation process is carried out by management.
<h3 /><h3>What is Risk?</h3>
Risk is the threat of things going wrong or having a negative impact on the operations of the organization. The risk can be of many types including and not limited to audit risk, control risk, credit risk, business risk, inherent risk, financial risk and more.
Risk is evaluated by the management to minimize the effects and mitigate the risk. There are several steps that are performed to analyze the risk and many ways are there to lower the effects of risk.
Risk resolution is the management strategies to analyze the risk and the best ways to mitigate the effects. Transfer the risk, avoid the risk by changing the decision, reduce and accept.
Learn more about Risk at brainly.com/question/27247805
#SPJ1
Answer:
depreciation rate per unit $0.34
Explanation:
To calculate the depreciation cost per unit we divide the amount subject to depreciation by the estimated untis production over its useful life:
depreciable amount:
$41,000 - $3,600 = $ 37,400
depreciation rate:
$37,400 / 110,000 units = $0.34
Answer:
Identify the sequence of tasks that take the longest to complete
Explanation:
Program Evaluation and Review Technique (PERT) is a project management tool that is used to manage potential contingencies in the process of executing a project. It is used to schedule ,organize and coordinate tasks in a project.
Determining the critical path on a PERT network lists out the time required for different tasks to be completed and as a result , the sequence of tasks that require the longest time are identified.