Answer:
Government policymakers decided to reduce the rate of inflation from 3% to 1.6%. As a result, the unemployment rate increased from 4.8% to 6.2%. The sacrifice ratio is:______
d. none of the above
Explanation:
a) Data and Calculations:
Old inflation rate = 3%
New inflation rate = 1.6%
Old unemployment rate = 4.8%
New unemployment rate = 6.2%
Ratio of old inflation rate to old unemployment rate = 3 : 4.8 = 0.625
Ratio of new inflation rate to new unemployment rate = 1.6% : 6.2% = 0.258
Sacrifice ratio = Difference between the two ratios = 0.367 (0.625 - 0.258)
b) The sacrifice ratio is the difference between the old ratio and the new ratio of inflation rate to unemployment rate.
Answer: Exclusive distribution
Explanation:
Exclusive distribution is defined as the agreement in which a parties involved are manufacturer and distributor.It states that the particular distributor cannot sell their service or item to any other party .It binds the agreement that product can be sold to the exclusive distributor.
According to the situation mentioned in the question, designers are asked for exclusive distribution by the retailer.Retailer does not wants that design of jewelry to be sold through any other source or retailer for effective sale.Thus agreement upon this matter is proposed by the retailer.
Answer:
Break-even point in total units= 951.7units
Explanation:
<em>Break-even point is the level of activity at which a firm must operate such that its total revenue will equal its total costs. At this point, the company makes no profit or loss</em>.
It is calculated using this formula:
<em>Break-even point (in units) = Fixed cost/ average contribution per unit</em>
<em> Blue Plaid</em>
Contribution per unit 43-30 = 13 52-45 = 7
<em>Average contribution per unit </em>
= ( (13× 4) + (7×5) )/9
= $ 9.66 per unit
<em>Break-even point in total units</em>
= $9200/$ 9.66
= 951.7units
Break-even point in total units= 951.7units
Answer:
It's c.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.