Answer:
"Network layer" is the correct answer to the given question .
Explanation:
The network layer is interconnected with different networks by providing permission to the network. This job is done by sending the packets in the network. The main aim of the network layer is to provide the logical addressing, routing, and fragmentation of packets.
The network layer is the layer of the OSI model whose primary function is moving the packets or datagrams in the internetwork which is connected by the routers.
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.
Answer:
See below
Explanation:
Because sometimes you have to 'carry' a 1 over to the ext column when adding two binary numbers
Example :
1 1 1
<u>+1 1 1 </u> <==== starting in the first R column add 1 + 1 to get 0 and carry 1
then the next column you will add 1 + 1 + 1 = 1 and carry 1 again
then 1 + 1 + 1= 1 and carry 1 again (to column 4) to get
1 1 1 0
The answer will be A they would wanna know about her work history