Answer: £ 81.38
Step-by-step explanation:
Given: On Monday,
5 builders took
hours ( i.e.
hours ) to build a wall.
On Tuesday, only 2 builders were available.
As workers are inversely proportional to the time if the job remains constant.
Inverse variation equation : 
Let x be the time taken by 2 builders, then


So, 2 builders will take 8.75 hours.
Each paid £9.30 for each hour.
Then, each builder will be paid for the work completed on Tuesday = £9.30 x 8.75
≈ £ 81.38
Hence, each builder will be paid £ 81.38 for the work completed on Tuesday .
Answer:
10 and 1/5
Step-by-step explanation:
11-4/5=10 and 1/5. x must be 10 and 1/5
Answer:
and 
Step-by-step explanation:
Let
x -----> the number of polyphonic ringtones
y ----> the number of standard ringtones
we know that
-----> equation A
-----> equation B
Solve the system of equations by substitution
Substitute equation A in equation B and solve for y





Find the value of x
<u>Given</u>:
Given that the data are represented by the box plot.
We need to determine the range and interquartile range.
<u>Range:</u>
The range of the data is the difference between the highest and the lowest value in the given set of data.
From the box plot, the highest value is 30 and the lowest value is 15.
Thus, the range of the data is given by
Range = Highest value - Lowest value
Range = 30 - 15 = 15
Thus, the range of the data is 15.
<u>Interquartile range:</u>
The interquartile range is the difference between the ends of the box in the box plot.
Thus, the interquartile range is given by
Interquartile range = 27 - 18 = 9
Thus, the interquartile range is 9.