Answer:
Time taken by A and B is 1.2 hr.
Explanation:
Given that
Time taken by tank when all(A+B+C) are open = 1 hr
Time taken by tank when A+C are open = 1.5 hr
Time taken by tank when B+C are open = 2 hr
If we treat as filling of tank is a work then
Work = time x rate
Lets take work is 1 unit
1 = 1(1/a+1/b+1/c) ---------1
1 = 1.5(1/a+1/c) ----------2
1 = 2(1/b+1/c) --------3
From equation 1 and 3
1=1(1/a+1/2)
a=2
Form equation 2
1 = 1.5(1/2+1/c)
c=6
From equation 3
1 = 2(1/b+1/6)
b=3
So time taken by
A is alone to fill tank is 2 hr
B is alone to fill tank is 3 hr
C is alone to fill tank is 6 hr
So
Time taken by A and B is 1.2 hr.
Answer:
1.33×10⁻¹⁰ N
Explanation:
F = GMm / r²
where G is the gravitational constant,
M and m are the masses of the objects,
and r is the distance between them.
F = (6.67×10⁻¹¹ N/m²/kg²) (1000 kg) (2000 kg) / (1000 m)²
F = 1.33×10⁻¹⁰ N
Answer:
The current is 2.0 A.
(A) is correct option.
Explanation:
Given that,
Length = 150 m
Radius = 0.15 mm
Current density
We need to calculate the current
Using formula of current density
Where, J = current density
A = area
I = current
Put the value into the formula
Hence, The current is 2.0 A.