Answer:
(B) $5,000 favorable.
Explanation:
Variable cost flexible budget variance:
budget for 6,000 units total variable cost: $180,000
We divide the total cost by the activity in that budget:
$180,000/ 6,000 = 30
Now we multiply by the actual volume:
5,000 x 30 = 150,000
Now we do flexible budget - actual cost = variance
150,000 - 145,000 = 5,000 favorable
It is favorable, as the cost where less than expected.
Answer: True
Explanation:
Decision regarding an asset replacement is usually based on both the internal rate of return and the net present value of the incremental cash flows.
Therefore, it should be noted that this brings about the complications when comparing the development of relevant cash flows to the expansion decisions.
Answer:
D. Ask the customer if they need any other products for the project.
Explanation:
Customers who buy pavers are usually involved in a medium or large house project, and probably need other products. For this reason, a sales representative should ask the customer if they need anything else for the project in order to increase sales for the company.
Answer:
The correct answer for option (a) is $1.15 and for option (b) is $1.33.
Explanation:
According to the scenario, the given data are as follows:
Present value (PV) = $1
Rate of interest (R) = 1.18% per month
Time period (for option a) (t1)= 12 months
Time period ( for option b) (t2)= 24 months
So, we can calculate the future value by using following formula:
FV = PV × ( 1 + R )^t
(a). By putting value in the formula:
FV = $1 ( 1 + 0.0118)^12
= $1 × 1.1511610877
= $1.15
FV = PV × ( 1 + R )^t
(b). By putting value in the formula:
FV = $1 ( 1 + 0.0118)^24
= $1 × 1.32517184983
= $1.33