Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
98.1% chance of being accepted
Step-by-step explanation:
Given:
sample size,n=56
acceptance condition= at most 2 batteries do not meet specifications
shipment size=7000
battery percentage in shipment that do not meet specification= 1%
Applying binomial distribution
<h3>P(x)=∑ᵇₐ=₀ (n!/a!(n-a)!)p^a (1-p)^(n-a)</h3>
In this formula, a is the acceptable number of defectives;
n is the sample size;
p is the fraction of defectives in the population.
Now putting the value
a= 2
n=56
p=0.01


=0.56960+0.32219+0.08949
After summation, we get 0.981 i.e. a 98.1% chance of being accepted. As this is such a high chance, we can expect many of the shipments like this to be accepted!
Answer:
see below
Step-by-step explanation:
14. We can represent 1 as √1 and 2 as √4 and because 1 < 3 < 4, we know that √3 is in between 1 and 2. However, 3 is closer to 4 than it is to 1 so √3 is about 2.
15. Again, 3 is √9 and 4 is √16. 9 < 10 < 16 so √10 is in between 3 and 4, however, since 10 is closer to 9 as it is to 16, we know that √10 is about 3.
16. -4 = -√16 and -5 = -√25, since 16 < 22 < 25, we know that -√22 is in between -4 and -5 but 22 is closer to 25 so the answer is -5.
17. -10 = -√100 and -11 = -√121 so -√120 is in between -10 and -11. Since 120 is closer to 121, the answer is -11.
Answer:
-8 + 7
Step-by-step explanation:
7 - 8 = -1
-8 + 7 = -1