Answer: False
Explanation:
Total Revenue is the total amount that is received in return on sales of goods and services.
It is calculated as Price multiply by Quantity.
If the price of a product increases the revenue would also increase ceteris paribus( all things being equal). If the price of a product was $10 and 4 units were purchased Total revenue would be $40 and if price increases to $20 and 4 units were still purchased total revenue would be $80 assuming that we’re not taking into consideration any other factor like elasticity or type of good.
If price increases revenue increases too.
Answer:
$1,070
Explanation:
Calculation to determine the amount of applied overhead is:
Using this formula
Applied overhead = Total cost of WIP - Direct materials - Direct labor
Let plug in the formula
Applied overhead= $3,550 - $1,610 - $870
Applied overhead=$1,070
Therefore the amount of applied overhead is:$1,070
Answer: ELYSE. TSA. AFP. <—- the one that has that in the first Column
Explanation:
TSA is very similar to AFP
The complete question should have been:
Malcolm Industries recently hired a large number of workers for the company's new construction factory in Colorado. During the hiring process, the management made a clear effort to recruit physically strong individuals because the work at the factory involves manual labor. The jobs need to be performed by individuals who have the energy and physical stamina to work for long hours. Which of the following surface-level characteristics did the company most likely concentrate on when selecting the new workers?
A.) Age
B.) Values
C.) Beliefs
D.) Religion
E.) Personality
Answer: Age.
Explanation:
Malcolm Industries made use of Age as the Surface Level Characteristic that determined who would be employed. A surface level characteristics can be defined as differences that individuals possesses that easily be identified when they are seen.
Answer:
Cost variance= 7 unfavorable
Explanation:
Giving the following information:
Each bat requires 1 kg of aluminum at $18 per kg and 0.25 direct labor hours at $20 per hour. Overhead is assigned at the rate of $40 per direct labor hour. Assume the actual cost to manufacture one metal bat was $40.
Estimated cost= 18 + 0.25*20 + 0.25*40= 33
Actual cost= 40
Cost variance= 7 unfavorable