Answer:
The EMV of this project is -17,500
Step-by-step explanation:
The EMV of the project is the Expected Money Value of the Project.
This value is given by the sum of each expected earning/cost multiplied by each probability.
So, in our problem

The problem states that there is a 25% chance of Snowmaggedon which will delay the project at a cost of $35,000. Since this is a cost,
is negative.

There is a 10% chance of cost of construction materials dropping saving the project $70,000. A saving is an earning, so
is positive

There is a 10% probability a labor strike will occur delaying the schedule with a cost of $40,000.

There is a 80% chance of new regulations mandated calling for higher inspection standards which will cost an additional $15,000 to mitigate


The EMV of this project is -17,500
3. tan(α) = height/distance
distance = height/tan(α)
distance = (648 m)/tan(13°) ≈ 1399.5 m
6. when y = |x| is translated 6 units down, 6 is subtracted from the y-value:
.. y = |x| -6
10. In point-slope form, the line through point (h, k) with slope m is
.. y -k = m(x -h)
For (h, k) = (10, -9) and m = -2, you have
.. y +9 = -2(x -10)
Answer:
126°
Step-by-step explanation:
the internal sum of the angles is always 180
28+26= 54
180-54= 126
Answer:
She payed $34.60.
Step-by-step explanation:
It cost $19.60, just to rent the bike.
Then multiply $6 × 2 (hours) = 12
Now 6 ÷ 2 = 3 (half hour)
Add 12 + 3 = 15
Add everything together
19.60 + 15
You then get $34.60.
Answer:
(a) (7, -3)
(b) (-7, 3)
Step-by-step explanation: