Answer:
A. Lowest Total Cost:
A. 315,550 or more
B. Lowest total cost of annual volume of 120 boats
C. C
Explanation:
The lowest total cost among the three alternatives is b.
If the company goes for new location it will have to incur fixed cost of $270,000 and variable cost per boat will be $600.
If the company Subcontracts then Total cost per boat is $2,620
If a company goes for expanding existing facility then it will incur fixed cost of $57,000 and variable cost will be $1,030 per boat.
If company produces 315,000 or more boats then it will have lowest possible cost for the boat.
For an output of 120 bots the best possible alternative is option C. The fixed cost will be $475 per boat ($57,000 / 120 boats)
The total cost will be $1,505 ($475 + $1,030)
A.exclusive it’s not an intense level of distribution
Answer: (D) Accept the risk
Explanation:
According to the given question, the one of the best solution is to accept the risk as the 2 given risks in the project cannot be removed or also outsourced from the given project scope.
Accepting the risk is one of the risk retention process in which we sometimes cannot avoid the given risk in the risk management and it is commonly found in the various types of investment process and also in the business.
On the basis of the given scenario, we could not eliminate the two risks in the project so the best solution is to using the risk acknowledgement due to some limitations. Therefore, Option (D) is correct answer.
Answer:
I'm on here most of the time.
Explanation:
If you'd like, I'll try to answer all of your questions! Just give me the word. :)
It is so they have more money for the business