Answer:
are costs that do not vary with production or sales level
Explanation:
Fixed cost can as well be regarded as overhead cost they are expenses in the company that does not depends on the change in the amount of goods and services produced in the company. They are time- related cost such as
salaries, property taxes, interest as well as insurance. It should be noted that fixed costs are costs that do not vary with production or sales level
If a customer has a concern about a product or service you can chat with the customer about their reservations with it and how they won't actually have an affect on the product or service. It is normal for consumers to be weary of a new product or service so helping their reservations be but to rest makes it easier to sell them the product or service.
Answer:
Millions of software programs have been created and have helped to improve the economy. This is an
example of___new technology___.
Answer:
the $$$ of the different thing will play a big part
<h3>
Explanation:</h3><h3>Part (a):</h3>
Solved part is attached as an image.
<h3>
Part (b):</h3>
Let us first determine the amount required of each item to produce 1 bracket.
From the attached diagram, we can see that to manufacture 1 bracket, quantity of each item needed is,
Base = 1
Spring = 2
Clamp = 1 + 4 = 5
Housing = 2
Handle = (1 * 1) + (4 * 1) = 5
Casting = (1 * 1) + (4 * 1) = 5
Bearing = 2 * 2 = 4
Shaft = 2 * 1 = 2
Hence, for 50 Brackets, quantity of each item required will be,
Base = 1 * 50 = 50
Spring = 2 * 50 = 100
Clamp = 5 * 50 = 250
Housing = 2 * 50 = 100
Handle = 5 * 50 = 250
Casting = 5 * 50 = 250
Bearing = 4 * 50 = 200
Shaft = 2 * 50 = 100
<em>NOTE: The above quantities give exclusive quantities required for each item. In actual practice, we won't have to purchase base, clamp & housing separately as the will be assembled from their components which are already procured.</em>
<h3>Part (c):</h3>
As 25 bases are already in stock, parts for them will not be needed. I will refer the quantities subtracted due to this by indicating (B). Similarly, quantities subtracted due to clamps will be indicated as (C).
Base = 50 - 25 = 25
Spring = 50
Clamp = 250 - 100 - 25(B) = 125
Housing = 100 - (2*25)(B) = 50
Handle = 1 * 125 = 125
Casting = 1 * 125 = 125
Bearing = 2 * 50 = 100
Shaft = 1 * 50 = 50