A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critic
al path is 90 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?
1 answer:
Answer:
required probability is .3446
Step-by-step explanation:
It is given that most expected time of completion = 90 days
Variance = 25
We know that

Thus the standard normal deviate is given by

Applying values we get

Using the standard table for Z we have probability corresponding to Z = -0.4 equals 0.3446
Thus required probability is .3446
You might be interested in
Answer:
Coef=6
Step-by-step explanation:
same i love them they are too dangerous
plz mark me as brilliant answer
12+25+45+65+34
= 181
Must click thanks and mark brainliest
Answer:
its 0 anyways lol
Step-by-step explanation:
Answer:
(5)(4)(3)(2)(1)= <u>120. </u>your answer will be 120
Step-by-step explanation: