Answer:
e. design programming
Explanation:
The planning techniques are responsible for structuring the tasks to be performed within the project, defining the duration and the order of execution of the same, while the programming techniques try to organize the activities so that the logical temporal relationships between them, determining the calendar or the moments of time in which each one must be realized. The programming must be consistent with the objectives pursued and respect existing restrictions (resources, costs, workloads).
The programming therefore consists in setting, in an approximate way, the moments of beginning and termination of each activity. Some activities may have slack and others are critical activities (fixed over time).
STEPS:
Build a time diagram (moments of beginning and slack of activities).
Establish the times of each activity.
Analyze project costs and adjust clearances (minimum cost project).
The average rate of change of distance over the time interval
3 ≤ t ≤ 6 represents the coin's average velocity over that interval.
Electric potential = work done/charge of electron = 2.18×10⁻¹⁸/1.6×10⁻¹⁹
= 13.625 V
Answer:
Work done, W = 0.0219 J
Explanation:
Given that,
Force constant of the spring, k = 290 N/m
Compression in the spring, x = 12.3 mm = 0.0123 m
We need to find the work done to compress a spring. The work done in this way is given by :


W = 0.0219 J
So, the work done by the spring is 0.0219 joules. Hence, this is the required solution.
The solution for this problem is through this formula:Ø = w1 t + 1/2 ã t^2
where:Ø - angular displacement w1 - initial angular velocity t - time ã - angular acceleration
128 = w1 x 4 + ½ x 4.5 x 5^2 128 = 4w1 + 56.254w1 = -128 + 56.25 4w1 = 71.75w1 = 71.75/4
w1 = 17.94 or 18 rad s^-1
w1 = wo + ãt
w1 - final angular velocity
wo - initial angular velocity
18 = 0 + 4.5t t = 4 s