A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?
1 answer:
Answer:
The standard deviation on the critical path = 0.834
Step-by-step explanation:
Variance of activity A ( ) = 0.33
Variance of activity B ( ) = 0.67
Variance of activity C ( ) = 0.33
Variance of activity D ( ) = 0.17
Thus the standard deviation on the critical path ( ) = + + +
= + + +
= 0.6956
= 0.834
The standard deviation on the critical path = 0.834
You might be interested in
Answer:
64
Step-by-step explanation
Answer:
$644.19
Step-by-step explanation:
just took the quiz
Answer:
12) 0.01 meter
13) B is the correct
Step-by-step explanation:
U answer it already the picture shows that it already been answer
Answer:
Step-by-step explanation:
a right triangle and hypotenuse consist of two legs. the two legs meet at a 90 degrees angle and the hypotenuse is the longest side of the right triangle