A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17).
What is the standard deviation on the critical path?
1 answer:
Answer:
The standard deviation on the critical path = 0.834
Step-by-step explanation:
Variance of activity A (
) = 0.33
Variance of activity B (
) = 0.67
Variance of activity C (
) = 0.33
Variance of activity D (
) = 0.17
Thus the standard deviation on the critical path (
) =
+
+
+ ![V^2_{4}](https://tex.z-dn.net/?f=V%5E2_%7B4%7D)
=
+
+
+
= 0.6956
= 0.834
The standard deviation on the critical path = 0.834
You might be interested in
B. -2 is the aswers
hope it help... :)
Answer:
9 pieces
Step-by-step explanation:
28 inches rope cut into 3-inch pieces
There is no matching answer choice, if given numbers are correct then the answer is 9 full pieces
---------
<u>Note:</u>
- The close answer choice is 8
- 28/8 = 3 1/2 or 3.5
- So if cut into 3.5 inch pieces then it is 8 full pieces
- just in case it was typo 3 instead of 3.5
Answer:
1 squared and 1 x squared
Step-by-step explanation:
I think that the best answer is A
Answer:
The equation for your graph is Y=2x+1