1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
bezimeni [28]
4 years ago
15

Order each set of values from least to greatest. 0.4,5/8,38%

Mathematics
1 answer:
Lostsunrise [7]4 years ago
7 0
0.4, 38%, 5/8

i changed them all to fractions to help me so:
0.4 =40%
5/8 = 62.5%
You might be interested in
Match the right side of the equation to the left side<br> cot x sec^4 x=cot x+ 2 tan x+tan^3 x
Natalka [10]

Step-by-step explanation:

cot x + 2 tan x + tan³ x

Write in terms of sine and cosine:

(cos x / sin x) + 2 (sin x / cos x) + (sin³ x / cos³ x)

Find the common denominator:

(cos⁴ x / (sin x cos³ x) + 2 (sin² x cos² x / (sin x cos³ x)) + (sin⁴ x / (sin x cos³ x))

Add:

(cos⁴ x + 2 sin² x cos² x + sin⁴ x) / (sin x cos³ x)

Factor:

(sin² x + cos² x)² / (sin x cos³ x)

Pythagorean identity:

1 / (sin x cos³ x)

Multiply top and bottom by cos x:

cos x / (sin x cos⁴ x)

Simplify:

cot x sec⁴ x

5 0
4 years ago
If y varies inversely as x and y=24 when x=8, find y when x is 4
olga2289 [7]
Y would equal 12 if x were to equal 4. You can think of it as a proportion.
6 0
3 years ago
Find the slope of the given points (6, -10) and (-15, 15). Show your work.
charle [14.2K]

Answer:

Step-by-step explanation:

The slope of a line between two points can be calculated by dividing the difference of y values by the difference of x values

in this case

m = \frac{y_2-y_1}{x_2-x_1} = \frac{15-(-10)}{-15-6} = \frac{25}{-21} = \frac{-25}{21}

6 0
3 years ago
An assembly line with 10 tasks needs be designed. The total time for all tasks is 16 minutes. If you need to produce 30 units/ho
Sindrei [870]

Answer: 8 minimum work stations is what would be needed.

Step-by-step explanation:

The cycle time is computed as the operating time daily divided by the scheduled output.

It is important to note that the daily capacity of the operation layout is the operating time divided by the cycle time.

Therefore,

If you need to produce 30units/hour.

The average cycle time is as follow:

The average cycle time is the average time between the completions of units.

60/30= 2 average cycle time

=16/2

=8

8 work stations is the minimum number that would be needed.

It is important to know that in an assembly line balancing, the minimum number of work station is the ratio of the sum of all tasks time to the cycle time.

5 0
3 years ago
Thirty
11111nata11111 [884]

Answer:

djriztos5islrula4p

Step-by-step explanation:

7epz7epsurs8tfoy

6 0
3 years ago
Read 2 more answers
Other questions:
  • Help me please And thank you
    7·2 answers
  • Help? -Factoring polynomials
    9·2 answers
  • Identify the height of the rectangle, given that A=(24x2+96x) ft2.
    10·1 answer
  • 1. 12 – 6 ÷ 2 + 1
    9·2 answers
  • In ΔPQR, m∠P = (3x+16) ,m∠Q=(4x-15),m∠R(2x+8) What is the value of x?
    12·1 answer
  • How do you find 2a+b?
    15·1 answer
  • Audrey bought 37 meters of fabric to make curtains for her customer. The fabric cost $750 per meter. When she arrived home she r
    10·2 answers
  • What is the area of a square with h=3in l=5in w=6in
    5·1 answer
  • Kaytelyn makes $10 an hour and receives weekly bonus of $25. How many hours dose she need to work this week to make more than $2
    15·1 answer
  • Does 7 = 0 ???????????????
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!