Going by 30 for east and -30 for west
Answer:
The triple constraint represents the three constraints or inputs which control the project's capacity to produce.
The three components are Budget, time, and scope.
The relationship between them is an interdependent or triangular shape.
Step-by-step explanation:
The triple constraint represents the three constraints or inputs which control the project's capacity to produce. Budget, Scope and Time.
- Budget - The budget describes the estimated cost of the project.
- Time: The time represents the deadline to complete the project.
- Scope: This is simply what needs to be provided.
These 3 components are dependent to each other.
For example, if time is restricted then scope and budget will be affected. similarly.
The relationship between the three is that one of the two other components must decrease while one component increases for the project to succeed as expected.
Answer:
Coordinates of other end point L = ( -19, 13 )
Explanation:
The mid point of the coordinates (a,b) and (c,d) is given by 
Here we have (a,b) = (1,-7) and
= (-9,3) , we need to find (c,d).

So coordinates of other end point L = ( -19, 13 )
The domain for the function is [10,∞) {x|x≥10}
Answer:
I'll think about it
Step-by-step explanation: