Answer:
December 31, year 9
Explanation:
Here, we want to state that date that is possible for Milo to acquire qualified replacement property.
In order to avoid being taxed on a gain resulting from an involuntary conversion, the property subject to the conversion must be replaced within a specified time, measured from the end of the calendar year in which the proceeds are received.
Generally, the period is 2 years, but it is 3 years when the involuntary conversion results from government condemnation or eminent domain and is extended to 4 years when the loss is in connection with a declared federal disaster area.
We are told from the question that Milo received the recovery on January 2, Year 5, the property would have to be replaced within 4 years from the end of Year 5 or by December 31, Year 9
The form of organization must the project manager be working in Functional.
<h3>What is the meaning of organization?</h3>
Organization refers to the group of the people working together in order to achieve organizational goal. The aim of every organization is maximization of the profits.
In the above case, the project manager is trying to complete a software development project but is unable to get the attention on the project. all the resources are under completion of the different works.
This implies that form of organization must the project manager be working in Functional because he has little powers to make the use of the resources.
Learn more about the project here:
brainly.com/question/15999858
#SPJ1
Product design but I’m also a little convinced it’s also product layout
Answer:
The amount to be paid for the contract today = $220,908.32
Explanation:
<em>The amount to be paid for the contract today will be equal to the present value of the annuity of $22,500 payable for 20 years discounted at a rate of 8% per annum.</em>
Present Value = A ×( 1 - (1+r)^(-n))/r
A- 22,500, r- rate of return - 8%, n -no of years 20 years
PV = 22,500 ×( 1-(1.08)^(-20) )/ 0.08
PV = 22,500 ×9.8181
PV = $220,908.32
The amount to be paid for the contract today = $220,908.32
Answer:
Results are below.
Explanation:
<u>First, we need to calculate the total cost of producing 2,900 units:</u>
Total cost= direct material + direct labor + allocated overhead
Total cost= (2*7)*2,900 + (0.5*16)*2,900 + [(0.5*16)*0.6]*2,900
Total cost= 40,600 + 23,200 + 13,920
Total cost= $77,720
<u>Now, the unitary standard cost:</u>
Unitary cost= total cost/number of units
Unitary cost= 77,720 / 2,900
Unitary cost= $26.8