Answer:
62.5%
Explanation:
We are given that
A ten-station transfer machine has ideal cycle time=30 sec=
Frequency of line=0.075 stops per cycle
Average time=4 min
We have to determine the line efficiency
Line efficiency=62.5%
Hence, the line efficiency=62.5%
...
I dont kno
Im so sorry
1
..... yes
Estimated number of indigenous faults remaining undetected is 6
The maximum likelihood estimate of indigenous faults is given by,
here,
= the number of unseeded faults = 6
= number of seeded faults = 30
= number of seeded faults found = 15
So NF will be calculated as,
And the estimate of faults remaining is = 12 - 6 = 6