Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
The factored form for this question is (5x-1)(x-5)
4 sqrt (32) + 6 sqrt (50)
4 sqrt (16*2) + 6 sqrt (2*25)
4 sqrt (16)*sqrt(2) + 6 sqrt (2)*sqrt(25)
4 *4*sqrt(2)+6sqrt(2)*5
16sqrt(2)+30sqrt(2)
46sqrt(2)
Ok. So, say you have 1 whole. If you take half of that it would be 50% or 0.50 of the whole. So with 1.34 you can turn it into 1 and 0.34. You have one whole, so that is 100 percent. You than add the 34 hundredths which is 34 percent. So you have 134%. Do you understand all that?
Answer: 255 calories hope this helps :)
Step-by-step explanation: