Answer:
Bank reconciliation for Miller Co. for August 31
Amount in $ Amount in $
Bank statement Balance 3,868
Add;
Deposits in transit 743
Bank service charge 115
Error in check for supplies 9 867
Deduct;
Outstanding checks 764
Cash account balance 3,971
Explanation:
The bank reconciliation is one done between the balance per the books and balance per the bank statement. This is usually as a result of transactions known as reconciling items.
These are items that have either been recognized in books but yet to be recorded by the bank or vice versa, transactions recorded wrongly by one of the parties etc.
To reconcile the two balance moving from the bank statement balance to the cash account balance;
Deposit in transit has been debited to the cash balance hence it will be added to the bank. Bank service charge has been deducted from the bank and will be added back.
The erroneous recorded of the check shows that the cash account balance was under credited by $9 hence it will added to the bank statement balance. The outstanding check has been deducted from the cash balance and will be deducted from the bank statement balance.
Answer:
The project manager can convince the project sponsors with the following reasons which are,
(1) Telling the sponsors the additional benefits that the team will have once a member enters the team.
(2)Informing the sponsors about the work not completed due to lesser number of workers.
(3)Informing the sponsors the additional benefits that the team will have once a member enters the team.
For on boarding a new worker the project manager does the following which includes:
(1)it is very necessary to share the agendas and charters of the previous meetings of the project to help individuals to familiarize with the project scope and goals.
(2)Having a one one meeting a with the individual and discussing with him/her about the project and solve his/her issues.
(3) Doing a formal introduction of the new member to both the project team and stakeholders of the project.
Explanation:
Solution:
In the half way of the project, the project manager can convince the project sponsors in the following ways shown below:
- Informing the sponsors about the work not completed due to lesser number of workers
- Informing the sponsors about the delays taking place due to shortage of members in the team
- Telling the sponsors the additional benefits that the team will have once a member enters the team
- Convincing the sponsors by discussing and talking with him/her the various drawbacks of not having the required numbers of members in the team.
For getting a new member on board for the project, it is very important to share the agendas and charters and minutes of the previous meetings of the project to enable individuals to familiarize with the project scope and goals.
Secondly, a one one meeting and discussion with the individual must be organized to brief him/her about the project and solve his/her issues.
Finally the new member must be introduced to both the project team and stakeholders of the project.
Answer:
B
Explanation:
In a private closed economy (actual) investment is equal to saving at all levels of GDP and equilibrium occurs only at that level of GPD where (planned) investment is equal to saving.
Answer:
=830.92/664.94=1.249616507
Explanation:
Answer:
False
Explanation:
Contingency approach, also known as situational approach, is a concept in management stating that there is no one universally applicable set of management principles to organizations. Organization's are individually different, face different situations, and require different ways of managing.