Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
Answer:
120°
Step-by-step explanation:
Answer:
second option
Step-by-step explanation:
The perimeter P is the sum of the 3 sides, then
P = 4x² + 3 + 2x - 5 + x + 11 ← collect like terms
= 4x² + 3x + 9
Answer:
1 year and 5 months
Step-by-step explanation: