Answer:
3482.12
Explanation:
Net present value is the present value of after-tax cash flows from an investment less the amount invested.
NPV can be calculated using a financial calculator
Cash flow = net income + depreciation = 16,200 + 3300 = 35,700
($56,100 - $7500) / 3 = 16,200
Cash flow in year 0 = 56,100
cash flow in year 1 and 2 = 35700
cash flow in year 3 = 35,700 + 7500
i = 5%
NPV =
Answer:
11. building codes
12. Consideration
13. Consumer Protection
14. Federal Unemployment Tax Act
15. Zoning laws
Explanation:
do you need help with 16 and 18? if you do please comment!! but hope i helped <3
Answer:
9
Explanation:
Given that
There is five stations who have the process time of 5,9,4,9 and 8
We need to find out the bottleneck time
so, as we know that the bottleneck is the duration of the activity who have longer time
So as per the given situation the 9 has the longest duration activity time
So, the same is to be considered
Answer:
d) $38,000 Debit balance.
Explanation:
Predetermined overhead rate = Estimated Total Overhead Costs / Estimated Direct Labor Costs
= $472000 / $2,360,000
= 0.2
= 20% of direct labor costs.
Applied overheads = (20%*Actual direct labor costs)
Applied overheads = 20% * $1,980,000
Applied overheads = $396,000
So, Overhead under-applied = $434,000 - $396,000 = $38,000 (Debit)
Answer:
Option (D) is correct.
Explanation:
Given that,
Beginning work in process = $4,000
Ending work in process in finishing department = $6,000
Cost transferred = $47,000
Direct material = $15,000
Direct labor = $46,000
Overhead = $22,000
Cost incurred in finishing department:
= Beginning work in process + Cost transferred + Direct material + Direct labor + Overhead
= $4,000 + $47,000 + $15,000 + $46,000 + $22,000
= $134,000
Cost of goods transferred to the Finished Goods Inventory account:
= Cost incurred in finishing - Ending work in process
= $134,000 - $6,000
= $128,000