Answer:
Programmed decision making
Explanation:
A programmed decision is one that is done by following already laid down rules and procedures. They are Carried out using formal patterns and the goals here are both clear and specific. These rules and routines in UPS are are a good example of how programmed decisions are done. As it can be seen on every aspect of their day to day business activities.
Answer:
D) Quantity sold rose while the effect on price is ambiguous.
Explanation:
Two separate things happened here;
- Change in consumer habits have shifted the the demand curve to the right, increasing the quantity demanded at every price level.
- Better technology and lower costs have also shifted the supply curve to the right, increasing the quantity supplied at every price level.
One thing is certain, the quantity demanded and supplied increased, so the total quantity sold definitely increased. The price issue is not certain because you would need additional information about which shift was larger, the shift of the supply curve or the demand curve.
Create test plan, develope scenarios, implement, summarize feedback, and retest.
This answer requires that we fill in the blanks
- The net present value (NPV) method estimates how much a potential project will contribute to shareholder wealth
- The larger the NPV, the more value the project adds; and added value means a higher stock price.
- The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted WACC
- When the firm is considering independent projects, if the project's NPV exceeds zero the firm should accept the project.
- When the firm is considering mutually exclusive projects, the firm should accept the project with the higher positive NPV.
What is the NPV?
In order to get the NPV we have to make the following calculations for the projects A and B.
This is calculated as
Project A
-900 + 620/1.08 + 395/1.08² + 200/1.08³ + 250/1.08⁴
= $355. 237
For the project B
We would have to perform similar calculation
Hence we would have
-900 + 620/1.08 + 395/1.08² + 200/1.08³ + 250/1.08⁴
= 378.98
From the calculations that we have done above, we can see that the value for project B is greater hence we have to choose project B.
Read more on NPV here:
brainly.com/question/17185385
#SPJ1
Answer:
Cost of goods sold is $ 11,500
Explanation:
cost of goods sold:
Opening stock: $3,500.00
Purchases: $12,000.00
Closing stock: $ 4,000.00
sales= Opening Stock+Purchases- Closing stock
=($3500+$12,000)-4000
$15,500-$4000= $11,500.00
Cost of goods sold= $11,500.00