Answer:
so so sorry I don't know
Explanation:
hope fully you'll get the answer
Change the font size
Change the font color
Change the background color
Adjust percentage of background shade
Add a hyperlink
Explanation:
All of these have todo with style
Answer:
The answer is "Option d".
Explanation:
The Iteration Management is also an activity in which all members of the team will determine how many the backlog team will allocate towards the next Iteration, and each team wraps up the work only as a group of determined iteration targets. in the given question the "choice d" is correct because The plans to achieve without training entered PO or design staff and requirements have not even been identified, and the wrong choice can be defined as follows:
- In choice A, T' he PO doesn't give the story detail, that's why it's incorrect.
- In choice B, the doesn't a team left the past for more refining with the PO in the Project Backlog, that's why it's incorrect.
- In choice C, The Development Team has not found some other team dependency, that's why it's incorrect.
Answer:
I believe it is just a task. Since there exists(on windows) the Task Manager application, where you can stop any running <em>task, </em>I think that they are called tasks
Explanation: