It takes 10 workers 5 days to complete a road repair when working 2 hours a day.
So, this becomes :
man hours required to finish the work.
Given is, if 2 people work for 5 hours a day, then let the number of days to finish the road be = d
So, total man hours = 
Now,
or 
Hence, it will take 10 days for 2 people working 5 hours daily, to complete the work.