The pressure difference across the sensor housing will be "95 kPa".
According to the question, the values are:
Altitude,
Speed,
Pressure,
The temperature will be:
→ ![T = 15.04-[0.00649(9874)]](https://tex.z-dn.net/?f=T%20%3D%2015.04-%5B0.00649%289874%29%5D)
→ 
→ 
now,
→ ![P_o = 101.29[\frac{(-49.042+273.1)}{288.08} ]^{(5.256)}](https://tex.z-dn.net/?f=P_o%20%3D%20101.29%5B%5Cfrac%7B%28-49.042%2B273.1%29%7D%7B288.08%7D%20%5D%5E%7B%285.256%29%7D)
→
hence,
→ The pressure differential will be:
= 
= 
Thus the above solution is correct.
Learn more about pressure difference here:
brainly.com/question/15732832
Answer:
The risk of catastrophic wildfire is a real and serious threat facing those who reside in the forested areas of Boulder County. Dating back to the Black Tiger Fire of 1989, wildfires have collectively destroyed some 250 homes or other structures, burned over 16,000 acres, and threatened the lives and properties of thousands of mountain residents. In an attempt to mitigate the loss of life and property in Boulder County, the Land Use Department has included wildfire mitigation measures in the planning review and building permit process.
Explanation:
Answer:
See explaination
Explanation:
We can describe Aspiration Effect as a phenomenon of providing an allowance for the release of air from the mold cavity during the metal pouring.
See the attached file for detailed solution of the given problem.
Answer:
Phase diagrams represent the relationship between temperature and the composition of phases present at equilibrium. An isomorphous system is one in which the solid has the same structure for all compositions. The phase diagram shown is the diagram for Cu-Ni, which is an isomorphous alloy system.
Hope it help you friend
Answer:
c) site preparation
Explanation:
A construction process can be defined as a series of important physical events (processes) that must be accomplished during the execution of a construction project.
Generally, in the construction of any physical asset such as offices, hospitals, schools, stadiums etc, the first step of the construction process is site preparation. Site preparation refers to processes such as clearing, blasting, levelling, landfilling, surveying, cutting, excavating and demolition of all unwanted objects on a piece of land, so as to make it ready for use.
This ultimately implies that, site preparation should be the first task to be accomplished in the construction process.
Hence, the construction process typically begins with site preparation before other activities such as the laying of foundation can be done.
Additionally, construction costs can be defined as the overall costs associated with the development of a built asset, project or property. The construction costs is classified into two (2) main categories and these are; capital and operational costs.