Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
x=2 AB=hypotenus(h) angle ACB is 90
BC=p angle CAB is 30 also angle of refrence
Step-by-step explanation:
sin[30]=p/h
(1/2)=x/4
2x=4
x=2
Answer:
I don't know if this helps, just a picture not a link
Any number to the power of 0 equals 1. Even if the original number is extremely high like 10000000, the value will still equal 1.