In phased construction, ______. all design is completed before construction begins foundation design always exactly considers th
e completely designed structure above building execution typically takes longer than in sequential construction building design may not be complete before construction begins a design/bid/build process is typically followed
building design may not be complete before construction begins
Explanation:
Phased construction is a form of construction methodology which involves the planning of various phases of work section at a time, instead of a conventional consecutive technique. It can be done using the following methods:
1. Through the work section
2. Through uneven completion rate among the various elements or stages of construction.
3. Through work category
Hence, in this case, In phased construction, building design may not be complete before construction begins