nadezda [96]
3 years ago
5

An analysis of the accounts of Roberts Company reveals the following manufacturing cost data for the month ended June 30, 2017 I

nventory Beginning EndingRaw materials $9,180 $17,480Work in process 5,670 7,610Finished goods 9,300 6,430Costs incurred: raw materials purchases $55,020, direct labor $51,740, manufacturing overhead $23,300. The specific overhead costs were: indirect labor $6,510, factory insurance $4,700, machinery depreciation $4,380, machinery repairs $1,990, factory utilities $3,740, and miscellaneous factory costs $1,980. Assume that all raw materials used were direct materials.Prepare the cost of goods manufactured schedule for the month ended June 30, 2017
Business
1 answer:
SSSSS [86.1K]3 years ago
7 0

Answer:

<u>cost of goods manufactured schedule</u>

Raw Materials ($9,180 + $55,020 - $17,480)          $46,720

Direct Labor                                                               $51,740

Manufacturing overheads :

indirect labor                                                               $6,510

factory insurance                                                       $4,700

machinery depreciation                                            $4,380

machinery repairs                                                       $1,990

factory utilities                                                            $3,740

miscellaneous factory costs                                       $1,980

Add Opening Work In Process                                 $5,670

Less Closing Work In Process                                  ($7,610)

Cost of goods manufactured                                 $119,800

Explanation:

Cost of goods manufactured schedule shows a summary of results (cost) obtained  from manufacturing activity during the production period.

You might be interested in
which component of effective high-performance teams is represented by the use of real-time feedback devices acls
ahrayia [7]

Answer: Quality

Explanation:

High-performance teams refers to the teams, or organizations which focuses on their goals and therefore achieve superior results and outperform other similar teams.

The component of effective high-performance teams that is represented by the use of real-time feedback devices is quality.

4 0
3 years ago
According to the commercialization stage of the new product development process, following the decision to introduce the new pro
aivan3 [116]

Answer: (A) Where to launch the new product

Explanation:

 The commercialization stage is the process of development the new products and the services in the market that can be used in solving the various types of life based problems.

The main objective of the commercialization stage is that it include the customer support, the production and the marketing for achieving the new products and the services commercial success in an organization.

according to the question, the commercialization stage is developing the new products and the services and then the company should decide where to introduce or launch the new services and the products.

 Therefore, Option (A) is correct.

4 0
3 years ago
Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and
Fiesta28 [93]

Answer:

Some financial details with which to calculate the bid price are missing,find them in the attached question.

The bid price if the predetermined overhead rates have applied is $112,473.00 as shown below

Explanation:

a) Plantwide Overhead Rate = Manufacturing overhead/direct labor cost=$1,543,610.00/$947,000.00

Plantwide Overhead Rate = $1.63

Total Manufacturing Cost = Direct Material + Direct Labor + overhead applicable

Total Manufacturing Cost = $18,700.00+$21,400.00 + $(21400*1.63 )

Total Manufacturing Cost = $ 74,982

Bid Price = Total Manufacturing Costs *1.5(150%)

Company's Bid Price = $74,982.00*1.5

Company's Bid Price = $ 112,473.00

5 0
3 years ago
Suppose that price is below the minimum average total cost (ATC) but above the minimum average variable cost (AVC) and that the
AysviL [449]

Answer:

b. continue to produce a quantity such that marginal revenue equals marginal cost.

8 0
3 years ago
Bezos moved to Seattle, Washington because _________ and ______
san4es73 [151]

Answer:

a

Explanation:

8 0
3 years ago
Other questions:
  • Jan. 3 Loaned $21,600 cash to Trina Gelhaus, receiving a 90-day, 7% note. Feb. 10 Sold merchandise on account to Bradford &amp;
    10·1 answer
  • How many people lost their jobs when the minimum wage increased from $12 to $18
    6·1 answer
  • Crystal Industries is considering an expansion project with cash flows of -$287,500, $107,500, $196,100, $104,500, and-$92,700 f
    6·1 answer
  • Unearned revenue, which represents the company's obligation to honor gift cards previously issued to customers, totaled $6,800 a
    12·1 answer
  • China had a $214 billion overall current account surplus in 2012. Assuming that China’s net debt forgiveness was zero in 2012 (i
    7·1 answer
  • Inflation is 14 percent. Debt is $4 trillion. The nominal deficit is $360 billion. What is the real deficit or surplus
    15·1 answer
  • Question 2 of 8
    15·1 answer
  • Prepare a monthly flexible selling expense budget for Cottonwood Company for sales volumes of $300,000, $350,000, and $400,000,
    10·1 answer
  • Prepare a classified year-end balance sheet, (Note: A $9,000 installment on the long-term note payable is due within one year.)
    15·1 answer
  • A ________ growth strategy employs the existing marketing offering to reach new market segments.
    7·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!